Oracle Invokes Force Majeure in Aim to Protect Itself From Data Center Cost Overruns
Oracle, which is set to lease a New Mexico data center on behalf of OpenAI, sent a notice to the project’s developer asserting its contractual rights to withhold payments if project delays persist, according to Bloomberg. Oracle sent a notice that cited “force majeure” to a developer owned by ...
Sources
- T1Oracle Invokes Force Majeure in Aim to Protect Itself From Data Center Cost OverrunsThe Information (teasers)